Fire-Rated Equipment Delivery Hatches for Doha Metro

Invicta ANARA designed and installed bespoke fire-rated equipment delivery hatches for five underground stations on Doha Metro’s Red Line South.

Project logo
Client
Doha Metro
Application
Transformer Equipment Delivery Hatches
Size
5m × 3m
Fire Rating
3 Hours
Acoustic Rating
30 dB

Company Background

Qatar Rail is a railway company owned and operated by the Government of Qatar. Established in 2011 as part of Qatar National Vision 2030, the company is responsible for designing, commissioning, building, operating and maintaining rail networks across the State of Qatar.

Its network includes Doha Metro, widely recognised as one of the world’s most advanced metro systems.

Project Challenges

Invicta ANARA had been appointed to design and install an over-track exhaust duct across five underground stations on Doha Metro’s Red Line South. As part of this wider project, the team had to accommodate a large opening in the concrete slab midway along the track area in each station.

Each opening measured 5m × 3m and was required to move transformer equipment from the platform level to the mechanical rooms on the intermediate level.

The openings needed to remain sealed during normal operation to help prevent fire, heat and smoke from spreading between levels. Invicta ANARA was therefore asked to develop a bespoke equipment delivery hatch that could maintain the required compartmentation while allowing access when equipment needed to be moved.

The original proposal involved precast concrete lift-out sections. This option was considered impractical because of the time required to remove them, their weight and the limited space available to manoeuvre and store them within the station.

Technical Constraints

Any equipment delivery or replacement work had to be completed during a five-hour engineering outage at night. The hatch therefore needed to open quickly enough to leave sufficient time for equipment movement and other required work.

The system also had to provide effective fire compartmentation and insulation in both directions. It needed to resist fire originating from the platform level in the event of a tunnel or station incident, as well as fire originating from the mechanical rooms on the intermediate level.

Space presented another important constraint. The mechanical rooms along the Red Line South were heavily congested with equipment, leaving little room to operate the hatch or permanently accommodate lifting machinery.

The closed hatch also needed to withstand people and equipment moving across its upper surface. From below, it had to resist the piston effect created by passing trains.

Installed Solution

Invicta ANARA designed and installed a bespoke two-leaf hinged equipment delivery hatch that met the project’s operational, fire and acoustic performance requirements.

Each hatch was 140mm thick and positioned on the concrete slab. The two leaves were connected to a perimeter frame fixed directly to the slab. The frame was finished flush with the screed to reduce trip risks and prevent obstruction when equipment was wheeled across the surface.

A specialist high-performance compact winch and pulley system was developed to operate the hatch. Each leaf could be opened in less than three minutes, allowing the system to be used comfortably within the five-hour engineering outage window.

The winch was mounted on a removable frame. It could be positioned whenever the hatch needed to be opened and removed for storage afterwards, preventing permanent obstruction within the congested mechanical room.

When raised into the vertical position, the hatch leaves could be secured to a supporting post to prevent accidental closure while personnel or equipment passed through the opening.

The completed system provided a three-hour fire rating and a 30 dB acoustic rating while maintaining the required access route between station levels.

Project Video

Invicta has proven to be a valuable partner for RLS-JV with its expertise, commitment and professionalism shown throughout the project and the works being delivered on time and to the highest standards

RLS-JV | Senior Project Director

RLS-JV | Senior Project Director